S3 EnterpriseFoundry

42 screens

Production

Making things: planning what to make, work orders through the floor step by step, what was made, what was used, and what it cost. Every page in the Production menu, what it is for, and where it leads; then the main records, tab by tab. The pictures are the demo company (Foundry Valves) after the test runs, so the names and numbers are made up. For the story, read How production works first.

Ways of making

A factory makes in one or more of these ways, switched on in Production options; the menu shows only the pages of the ways switched on:

WayForIts pages
Work ordersMade against an order, step by step on the floor (machining, assembly, fabrication)Work orders, Shop floor, Inspection, Material, Receive made...
Making in one stepParts out and the item in, in one entry (simple assembly, packing)Make in one step
CuttingPlate, bar and coil cut into partsCutting, Nesting
Batches from recipesChemicals, paints, food, pharmaWork orders with a batch
Lines and machinesA daily report a machine and shift; moulds and dies with their shotsDaily production, Tools

How making goes

Sales order or forecastPlanning (what to make, what to buy, by when)Work orders
Work orderMaterial issuedEach step booked on the floorInspectionReceive madeInto stock
PlanningRequisitions for what is short (Purchase)
Work orderA step done outsideJob work challan (Purchase)Back, its labour billed

The work

Making

Jobs

Each sales order line being made here, from the customer's side: how many made of how many, where it is now (not planned, waiting for material, at a step, made), how far, and when it can finish. Late ones first.

Jobs

Work orders

Every order to make something: the item, how many made, the step it is at, whether its material is in or short, its stage, what it is for (stock or a customer's order), when it is due and when it can finish. Late and Material short narrow it.

Work orders

Shop floor

The supervisor's booking sheet for a shift: each slip - the order, the step, good and rejected - booked in one go. Queue shows what waits at each work centre.

Shop floor

Worksheets

A machine's plan for a shift: the jobs to run on it, how many to make, and what was booked against each.

Worksheets

Run values

Readings taken while making - a bore size, a test pressure, a mould temperature - against their limits. One outside its limits shows in red. Out of limits only narrows it.

Run values

Energy

Power used by each meter a day, its cost, the good pieces made, and the energy a piece.

Energy

Nesting

A cutting machine's nesting program: the sheets it cuts, the parts it makes, cut length, time and waste.

Nesting

Boxes

Made goods packed in boxes with a number each - in stock, used, dispatched - so a box can be moved and labelled as one.

Boxes

Inspection

Every inspected step with pieces waiting: the inspector passes, rejects or sends them to rework, with the readings the step asks for.

Inspection

Job work

Steps done outside: what is to send to a job worker, what is out, what is to receive, what is to bill, and tools lent out. Scorecard shows how each job worker does.

Job work

Material

Every open work order and its material: all there, or which parts are short. Tick orders, Issue their material, print a Pick list, or Requisition the shortage.

Material

Receive made

What has passed its last step and is ready to go into the store: tick, pick the store, Receive. Close short ends an order that will make less.

Receive made

Cutting

Plate, pipe and bar cut into parts: what was cut from, kg cut, parts made, offcut and scrap, and the yield. What to cut and Offcuts show what is waiting and what is left.

Cutting

Make in one step

For something made all at once: pick the item and how many, its parts come out of their stores, it goes in - every step done in its planned time.

Make in one step

Daily production

A machine's report for a day and shift: the item, the tool (mould or die), the shots, good and rejected, and the downtime with why.

Daily production

Unbuild

A made item taken apart by its bill of material: it leaves its store, its parts come back sharing its value.

Unbuild

Planning

Planning

Run the plan: it looks at open sales orders, stock minimums and open work orders against stock and what is on order, and says what to make, what to buy, what to move and when to start each. Firm turns the plan's lines into work orders and requisitions. Shortages lists what is short.

Planning

Capacity

Each work centre's load day by day - how full its hours are with the work orders on it. Schedule sets each order's steps into the days; Board shows them to move about.

Capacity

Work order stages

Where each open order stands in its stages (material ready, making, inspection, the customer's inspection call, into the store) against the target date of each, late ones first.

Work order stages

Labour

What each skill (welder, fitter, helper) still owes the open orders: their waiting pieces times the minutes a piece set on the BoM steps.

Labour

Sales forecast

What we expect to sell of an item in a month, so the plan makes ahead of the orders.

Sales forecast

Production plan

How many of each item to make a month (or week), typed by hand; Save the plan and the planning run takes it as demand. Make work orders makes them straight.

Production plan

Masters

Work centres

Where work is done - a machine, a bench, a line - with its cost an hour (what an hour there adds to a product's cost) and how many hours a day it runs.

Work centres

Tools

Moulds, dies and jigs: what each makes, its cavities, shots used and since its last repair, where it is now.

Tools

Operations

The steps used in BoMs (machining, painting, hydro test) and the work centre each is usually done at.

Operations

Job work rates

What each job worker charges for a process, and how many days it takes.

Job work rates

Workshops

The shops of a factory - machine shop, fabrication bay, assembly hall - that work centres stand in.

Workshops

Holidays

Days the factory is shut, so planning skips them.

Holidays

Shifts

Each shift's hours and break.

Shifts

Floor people

Operators, technicians, supervisors and inspectors on the floor, with their trade.

Floor people

Floor defaults

For each person who books: their usual workshop, shift, supervisor and inspector, filled in for them.

Floor defaults

Manpower days

Working days and man-days a month - the labour cost is spread over them.

Manpower days

Energy meters

Power meters, the machine each measures and the rate a kWh.

Energy meters

Meter readings

Each meter's reading a day; the difference is the power used.

Meter readings

Backflush stores

Where parts used up as they are made are taken from, store by store in order.

Backflush stores

Stage templates

The stages an order goes through, with the days each takes - laid on each work order to watch it by.

Stage templates

Reports

Production reports

Every production report, down the left: work in progress (each order, its material and time cost so far), production registers, rejections and their reasons, downtime, efficiency, costs of what was made.

Production reports

Shortages

What the plan found short: needed, free, coming, short, from when, and for which order.

Shortages

Settings

Production options

The ways of making switched on; whether an order line's work orders may make more than it ordered; what every booking must carry (start and end times, a remark, its checks ticked); who may book where.

Production options

The main records, tab by tab

Work order

What it makes, how many, made so far, needed by, for which order. At its foot: Print, Change, Cancel, Sub-assembly orders (orders for its made parts), Close short, Issue (its material) and Receive. Tabs:

Work order
  • Steps: each step, where, how many reached it, good, rejected, rework, waiting and minutes used against planned; the bookings, each one that can be taken back
  • Material: each part needed, issued, used, still to issue, from which store, held, short, requisitioned, ordered; Issue, Return, Hold stock, Requisition the shortage, Change material
  • Stages: its stages with their target dates, who is responsible, and Done
  • Pieces: each piece numbered, followed through the steps
  • Received: what it put into the store
  • History: every step with when
its tabs

Job

A sales order line seen from the floor: how many ordered, made, dispatched, when it can finish, where it is; its work orders (the item and its made parts) with each one's step and material; and its BoM line by line - needed, issued, held. Hold material keeps stock for it.

Job

Worksheet

A machine and shift, and the jobs to run: each order and step, how many to make, operator, supervisor, minutes, from and to, and Book what was done. Fill from the schedule brings in what was planned for it.

Worksheet